What's Next?

Since then a number of people have been working extremely hard working out what to do next.. We’ve now worked it out. This is what needs to happen before we move forwards into church: -

Phase 1 - Removal of ceiling tile debris

Phase 2 - Low level clean of nave and chancel

Phase 3 - Remove, clean and temporarily store all furniture

Phase 4 - Dispose of any porous materials that cannot be cleaned (such as electrical equipment, fabric and carpet)

Phase 5 - Instal scaffolding to get up to the ceiling. This kind of scaffolding is known as either a bird cage, dance floor or crash deck.

Phase 6 - High level clean of roof and ceiling joists

Phase 7 - Removal of the entire AIB ceiling

Phase 8 - Removal of all loose lath and plaster

Phase 9 - Instal new ceiling made of plasterboard

Phase 10 - Dismantle scaffolding

Final clean of the building

Sign off by HSE

Put back the furniture

We hope to be able to announce in the very near future that a contract has been awarded for the works which will then take about 4 months to complete. Watch this space!